GMAT Graphic Interpretation Practice 16

settings  Settings
close
BestMyTest GMAT course is developed by a team of certified GMAT teachers from across the globe. Here, you can seek guidance and ask questions directly to our team of experienced instructors.

Get 5 Ask Instructor questions as a reward
for singing up free today.

close Filter
search
 
Diffculty: Easy

The chart shows a firm's complete time-and-task schedule for the marketing team, planning team, and development team involved in the launching of a new product.

Based on the information in the graph, select from each drop-down menu the option that creates the most accurate statement.

The number of weeks the planning team has two tasks scheduled is percent of the total number of weeks the planning teams are involved.

To the nearest 5 percent, the number of weeks the development team has at least one task scheduled is percent of the total duration represented by the chart.

is the only week during which three different tasks are scheduled to begin.